Sprint Retrospective Meeting

Project: Spear Phishing, OSINT Bot
Attendees:  Alexander, Andres, Andrew, Jasen
Start time: 5:00
End time: 5:41

What went wrong?
Did we do a good job estimating our team's velocity?
The completed their later than expected. However, we did finished with time to spare.

Did we do a good job estimating the points (time required) for each user story?
The estimation of points per user story was off, but not by large margins.

Did each team member work as scheduled?
Each team member work according to scheduled with some minor setbacks.
